What are G98 and G99?
G98 and G99 are Engineering Recommendations (EREC) published by the Energy Networks Association (ENA). They set the rules for connecting generation equipment, including home batteries and solar inverters, in parallel with Great Britain's distribution networks. G98 covers fully type-tested micro-generators up to and including 16 A per phase. G99 covers equipment that is not in the scope of G98 or does not meet it (EREC G99 Issue 2).
A home battery counts here even if you have no solar panels. The ENA guide says DNOs treat electricity storage as generation when they assess the impact on their network, so storage has to meet G98 or G99 depending on its capacity (ENA Distributed Generation Connection Guide). The DNO is the company that runs the local wires, not the supplier that sends your bill.
G98 vs G99 comparison table
| G98 | G99 | |
|---|---|---|
| Size limit | Up to and including 16 A per phase: about 3.68 kW single phase, 11.04 kW three phase, total at the property (ENA G98 guide) | Above 16 A (3.68 kW) per phase, or equipment that does not meet G98 (NGED G99 procedures) |
| Process | Install and notify. You do not need to talk to the DNO before the system is running (ENA G98 guide) | Apply first, connect only once the DNO confirms its assessment is complete (SSEN) |
| Paperwork | Installation Document (Form B), sent no later than 28 days after commissioning (EREC G98) | Fast track: Form A1-2, then Form A3-2 within 28 days of commissioning. Standard route up to 17 kW single phase or 50 kW three phase: Form A1-1 (NGED, ENA) |
| Typical timeline | No wait for approval. Notification follows the install, within 28 days (EREC G98) | Fast track: DNOs such as SSEN and NGED aim to reply within 10 working days (SSEN, NGED). Standard: up to 45 working days for a quotation with LV works (SSEN guaranteed standards) |
| Can the DNO say no? | No approval step, but the equipment must be type tested and the total must stay within 16 A per phase (ENA G98 guide) | Yes. The DNO confirms whether the connection is or is not acceptable, and can set conditions (ENA guide, SSEN) |
| Who does it? | Your installer (EREC G98) | Your installer usually applies on your behalf, the DNO decides (SSEN) |
Going down the G99 route? Our G99 application guide for home batteries walks through the forms, what the DNO looks at and how to avoid delays.
The 3.68 kW threshold explained
The limit in G98 is written as a current: up to and including 16 A per phase. On a 230 V single-phase supply, 16 A works out at 3.68 kW (230 V × 16 A = 3,680 W). On a three-phase supply it is 11.04 kW in total. The ENA guide gives both figures and makes clear they apply to the total generating capacity at one property, not to each device (ENA G98 single premises guide).
For inverter-connected kit, the rating that counts is the inverter's continuous steady state rating. National Grid Electricity Distribution gives a worked example: a single-phase 4 kW inverter is 4,000 ÷ 230 = 17.39 A, just over the 16 A threshold, so it falls under G99 (NGED G99 connection procedures).
Does battery capacity affect G98 or G99?
No. G98 and G99 are about power, measured in kW or amps per phase, not storage measured in kWh. The DNO looks at the inverter's rating, because that sets how much power can flow to or from the network at any moment (NGED). Battery capacity only decides how long the battery can keep that power up.
This matters when you compare systems. A large battery behind a small inverter can stay inside G98. A smaller battery behind a bigger inverter can push you into G99. Always ask for the inverter's rated output, not just the kWh figure.
Already have solar panels? Adding a battery can mean G99
G98's 16 A limit is the total for the property. If you already have a solar inverter and add a battery inverter, the two ratings are added together. The ENA guide says that when storage is used alongside solar, the total is likely to be above 16 A per phase, so G99 applies (ENA Distributed Generation Connection Guide).
That is where the G99 fast track helps. Since November 2022, small installations that use fully type-tested inverters and stay within 32 A or 60 A per phase in total (depending on the category) can use a shorter application on Form A1-2 (ENA). Some categories need an export limitation scheme under EREC G100 that caps what the property can send to the grid (NGED fast track). The ENA guide also notes that storage designed to run in island mode during a power cut cannot use the fast track and goes through the standard G99 process (ENA guide).
How long does G99 approval take?
It depends on the route. On the G99 fast track, SSEN and National Grid Electricity Distribution both say they aim to respond within 10 working days (SSEN, NGED), and the ENA describes the fast track as cutting the DNO's answer from 45 days to 10 days or less (ENA guide). For a standard application that needs a quotation with low voltage network works, the guaranteed standard is 45 working days, roughly nine weeks (SSEN guaranteed standards, April 2026).
Under G98 there is no approval wait at all. Your installer can commission the system and notify the DNO afterwards, within the 28 days (ENA G98 guide). On the fast track, the planned commissioning date on the form has to be between 10 working days and three months after the application goes in (ENA). Installers can also apply through ENA Connect Direct, a single online form used by the UK's DNOs. It can auto-approve applications that pass its checks and sends the rest to a DNO connection engineer.
Which DNO covers my area?
The ENA's find my network operator tool tells you from your postcode, or from the Distributor ID at the start of the MPAN on your electricity bill. In England, Scotland and Wales you can also call 105 for free to reach your DNO. The six GB operators listed by the ENA are UK Power Networks, National Grid Electricity Distribution, Scottish and Southern Electricity Networks, SP Energy Networks, Northern Powergrid and Electricity North West (ENA). Each has its own forms and inboxes, but equipment connected to any of their networks has to comply with the same ENA G98 and G99 documents (SSEN).
What does your installer need to do?
For G98, the installer commissions the system and sends the DNO the Installation Document, Form B in Appendix 3 of EREC G98, no later than 28 days (including the day of commissioning) after commissioning (EREC G98 Issue 2). Some DNOs use their own version of the form. Manufacturers of G98 equipment have to lodge their declarations of compliance on the ENA LCT Register, so your installer can check the exact model (ENA). The older ENA Type Test Register closed in April 2024 and its data moved into Connect Direct (ENA guide).
For G99, the installer sends the application before any connection is made. The DNO may ask for more information, such as a schematic, type test certificates or details of an export limitation scheme, and you cannot connect until it confirms its assessment is complete (SSEN G99 fast track).
Where Habo's EcoFlow STREAM fits
Habo fits the 5 kWh EcoFlow STREAM, an all-in-one with the inverter in the unit. EcoFlow UK lists a maximum grid-connected output of 2,500 W for a single STREAM AC 5000, or 3,000 W when it is stacked with an Expansion Battery 5000, and 3,000 W for a single STREAM 5000 (EcoFlow UK STREAM AC 5000). All of those sit under the 3,680 W G98 line for a single-phase home, so one main unit on its own fits the G98 notify route. Your electrician still checks what else is already connected at the property, because the 16 A limit is a total. EcoFlow also says one system can link up to six main units (EcoFlow UK), so several units together could cross into G99.
EcoFlow says the STREAM must be hardwired into your consumer unit by a certified, registered electrician in the UK, and should not be plugged into a household socket to feed power in (EcoFlow UK). The electrician who wires it also sends the G98 notification. See our guide to UK home battery installation rules for the wiring side.
Best case, the 5 kWh STREAM at £2,499 fully installed saves up to about £450 to £530 a year on Octopus Go. Think of that as the interest you would earn on £2,499 in a savings account: about 18.1% to 21.1% a year (see how we worked it out, using Octopus Go 12M Fixed rates checked 15 October 2026). It assumes one full cycle every day, so real savings will be lower. For the full comparison, see home battery vs savings account. For help choosing a size, see what size battery you need.
Frequently asked questions
G98 covers type-tested equipment up to and including 16 A per phase (about 3.68 kW single phase or 11.04 kW three phase, in total at the property). Your installer fits it and notifies the DNO within 28 days. G99 covers anything bigger, or anything that does not meet G98, and the DNO has to approve the connection before the system is switched on (ENA G98 guide, SSEN).
G98 is written as 16 A per phase. On a 230 V single-phase supply that is 3.68 kW, and on a three-phase supply it is 11.04 kW. The limit is the total of all generation and storage at one property, not each device (ENA G98 single premises guide).
G99 is the ENA Engineering Recommendation for connecting generation and storage that falls outside G98. If your battery inverter, or your battery and solar inverters added together, go over 16 A per phase, your installer must apply to the DNO and wait for confirmation before connecting (NGED G99 procedures, SSEN). Our G99 application guide covers the steps.
On the G99 fast track for small type-tested systems, SSEN and National Grid Electricity Distribution aim to respond within 10 working days (SSEN, NGED). A standard application that needs a quotation with low voltage network works has a guaranteed standard of 45 working days, roughly nine weeks (SSEN guaranteed standards, April 2026). G98 has no approval wait.
No. The test is power, so the inverter's continuous rating in kW or amps per phase decides it. For example, NGED says a single-phase 4 kW inverter is 17.39 A, just over the 16 A G98 limit (NGED). A large battery behind a small inverter can still sit within G98.
Often, yes. The 16 A limit is the total for the property, and the ENA guide says storage used alongside solar is likely to take the total above 16 A per phase, so G99 applies. These homes may be able to use the G99 fast track, which cuts the DNO's answer to 10 days or less, but storage designed to run in island mode during a power cut goes through the standard G99 process (ENA Distributed Generation Connection Guide).
Your installer. Under G98 the installer must make sure the DNO is told no later than 28 days after commissioning, using the Installation Document (Form B) (EREC G98 Issue 2). For G99, the installer usually submits the application on your behalf before any connection is made (SSEN).
Not usually for one unit on a single-phase supply. EcoFlow UK lists a maximum grid-connected output of 2,500 W for a single STREAM AC 5000, or 3,000 W with an Expansion Battery 5000, below the 3,680 W G98 limit (EcoFlow UK). If you already have solar or other generation, or link several main units, the total could go over 16 A per phase and your electrician would look at G99 instead.
Keep an eye on UK battery prices
Leave your email for occasional updates on UK home battery prices, tariff changes and the 0% VAT deadline. No spam, unsubscribe any time.
Thanks, you're on the list.
Simple battery, simple install
Electrician-wired EcoFlow STREAM from £2,499. Join the UK-wide waitlist and Habo will try to book you in wherever one of our electricians can take the job. Nothing to pay today.
Join the waitlist